Site 3 = Middleton of Blackford 49.9MW
(already approved, construction not yet started)
Owner = Noriker Power (45% owned by Equinor formerly known as Statoil)
Physical Size = 1.88 Acres (0.76 ha)
Planning went in = 11/01/2023
Planning Approved = 07/09/2023
Time line for construction = ??
How long lease period = 25 years
Power Output = 49.9MW (61.4MVA)
Capacity = 108-208Mhrs
Aberdeenshire Planning Application Number - APP/2023/0718